By Matthew DeVries on August 9, 2010

It can be a daunting task to mine through the federal and state laws, regulations and court decisions to determine what rights and remedies you may have as a disappointed bidder on a public project.   In a case involving a state university construction project, the Ohio Supreme Court recently provided a good road map of what do in such situations.

Ohio Supreme Court Provides Road Map to Rejected Bidders

In Meccon, Inc. v. University of Akron (pdf), a contractor sought a temporary restraining order and other relief resulting from the university’s failure to award it the HVAC contract.  The facts of Meccon are intricate because the project involved multiple scopes of work that could be submitted by offerors as stand-alone bids or combined bids.  Ultimately, the contractor alleged that the university wrongfully awarded three of the stand-alone bids to the awardee—after the awardee had withdrawn its combined bid—which was in violation of the university’s own “Instructions to Bidders” documents and public bidding statutes.  The contractor sought injunctive relief, as well as damages for its bid-preparation costs.

  • Posted in:
    Real Estate & Construction
  • Blog:
    Best Practices Construction Law
  • Organization:
    Matthew DeVries
  • Article: View Original Source

Open Legal Blog Archive, Inc. logo
Seattle, Washington
Copyright © 2026, Open Legal Blog Archive, Inc. All Rights Reserved.
Law blog design & platform by LexBlog LexBlog Logo